Search projects

Learn about current transportation network improvement and preservation activities throughout the state.

You might be looking for studies or local agency managed projects

Filter projects

Select
Select
Select
Select

348 results

Project

US 101/Delphi Rd to I-5 - Paving and Concrete Barrier - Complete October 2022

Timeline: May 2022 - October 2022
  • Road
  • Completed
  • Thurston County
Workers repaired the surface of southbound US 101 in areas between Mud Bay and US 101 in Tumwater. Crews also made safety improvements on the southbound US 101 ramp to northbound I-5 in Tumwater
Project

US 101/Hoquiam River-Riverside Ave Bridge - Machine Rooms Rehab - Complete November 2023

Timeline: Spring 2023 - Fall 2023
  • Road
  • Completed
  • Grays Harbor County
This project repaired and upgraded two machine rooms that house equipment that operates the US 101 Hoquiam River Riverside Bridge in Grays Harbor County.

Work included repairs to the existing machine rooms, removing and replacing the old machine room walls and roof, and painting the…
Project

US 101/Northwest US 101 – Remove Fish Barriers

Timeline: Spring 2024 - Fall 2025
  • Road
  • Construction
  • Jefferson County
  • Clallam County
This project will replace culverts under US 101 in Clallam and Jefferson Counties.
Project

US 101/South of Forks - Emergency Repairs - Complete August 2022

Timeline: Spring - Summer 2022
  • Road
  • Completed
  • Clallam County
  • Jefferson County
This project will make repairs to the roadway on US 101 south of Forks near the Jefferson-Clallam County border. Work at this site includes: rebuilding the washed-out area of highway, rebuilding and reinforcing the slope and drilling new drains into the hillside. An emergency contract will be…
Project

US 101/SR 116 North Olympic Peninsula – Remove Fish Barriers

Timeline: Fall 2024 - Fall 2026
  • Road
  • Construction
  • Clallam County
This project removes and replaces several outdated culverts under US 101 and State Route 116 at Lees, Ennis, Tumwater and Chimacum Creeks. Washington State Department of Fish and Wildlife has identified these sites as barriers to salmon migration and other resident fish species.

Project

US 12 - Nine Mile Hill to Frenchtown Vic - Build New Highway - Complete June 2023

Timeline: 2016 - 2023
  • Road
  • Completed
  • Walla Walla County
This section of US 12 is located north of the communities of Touchet and Lowden. To maintain access to these communities, two interchanges were constructed with local roads including the existing US 12 at the bottom of Nine Mile Hill and Lower Dry Creek Road. Bridges were constructed to maintain…
Project

US 12 - SR 8 - Grays Harbor County Fish Passage Barriers - Remove Fish Barriers

Timeline: Spring 2023 - Winter 2025
  • Road
  • Construction
  • Grays Harbor County
This project replaces five outdated culverts under US 12 and State Route 8 in Grays Harbor County between Montesano and the Thurston County line for improved fish migration.

Project

US 12 - Wallula to Nine Mile Hill - Build New Highway

Timeline: Spring 2027
  • Road
  • Pre-construction
  • Walla Walla County
Since 2003, WSDOT and the US Highway 12 Coalition have made significant progress towards widening US 12 from two to four lanes between the Snake River (near Burbank) to Walla Walla. Phase 8 will complete the approximately 10 miles of new four-lane divided highway that remain between Packaging…
Project

US 12 - Wishkah River Bridge - Mechanical Rehabilitation

Timeline: 2025-2029
  • Road
  • Not started
  • Grays Harbor County
This project addresses worn mechanical components of the bridge that need replacement. In order to do this important work, the bridge will need to remain in the “down” position which prohibits larger marine vessels from traveling up or down the river.

During construction, travelers…
Project

US 12 Gordon Road Bridges – Deck Rehab

Timeline: Late Summer 2023 - Fall 2024
  • Road
  • Construction
  • Yakima County
This summer, crews will repair the westbound bridge deck on US 12 located above Gordon Road between the North 16th Avenue and North 1st Street exits in Yakima. Crews will also repair the westbound I-82 off-ramp to North 1st Street.
Project

US 12/Clear Fork Cowlitz River & US 97/Bickleton Rd – Bridge and Deck Rehab

Timeline: August 2022 - September 2024
  • Road
  • Completed
  • Klickitat County
  • Lewis County
This project rehabilitated the concrete deck of the US 12 bridge over Clear Fork Cowlitz River near Randle, WA in Lewis County and the US 97 bridge over Bickleton Hwy near Goldendale, WA in Klickitat County. Contractor crews repaired damaged areas and applied an overlay to the decks with fresh…
Project

US 195 - Old BNRR Bridge to Jct. SR 271 - PCCP - Complete June 2023

Timeline: May 2022 - Spring 2023
  • Road
  • Completed
  • Whitman County
This project is located on US 195 in Whitman County between milepost 52 near the Cashup Flatts Weigh Station and milepost 62, just south of the SR 271 interchange. Cracked and damaged concrete panels will be replaced along this stretch of roadway. The roadway will also be diamond ground to remove…
Project

US 195 – Babbit Road to Colfax Paving - Complete August 2023

Timeline: July 2023 - September 2023
  • Road
  • Completed
  • Whitman County
This project will rehabilitate approximately 8.5 miles of US 195 from Babbit Road to Colfax in Whitman County. Once the project is completed by grinding and inlaying new HMA (Hot Mix Asphalt), the roadway surface will have a smoother ride that will be preserved for years to come.
Project

US 195 – Colfax North Fork Palouse River – Replace Bridges

Timeline: Summer 2025 - Summer 2027
  • Road
  • Not started
  • Whitman County
The Washington State Department of Transportation (WSDOT) is in the early design phase of replacing the two bridges that cross the North Fork of the Palouse River, with a new single bridge structure, as they have reached the end of their expected service life.
Project

US 195 – Cornwall Road to Cheney-Spokane Road – NB Lanes Only – Paving

Timeline: August 2024 - Summer 2025
  • Road
  • Construction
  • Spokane County
This project will rehabilitate roughly 11 miles of northbound US 195 from Cornwall Road to Cheney-Spokane Road in Spokane County. This project will grind and inlay new HMA (Hot Mix Asphalt), the roadway surface will have a smoother ride that will be preserved for years to come.
Project

US 2 - Bickford Ave to Gold Bar - Paving & Joints & Improvements & ADA - Complete September 2021

Timeline: December 2018 - spring 2021
  • Road
  • Completed
  • Snohomish County
In 2019, WSDOT will spend $15.6 million on safety improvements and preservation efforts along nearly 25 miles of US 2 from Bickford Avenue to Gold Bar. As part of this project, contractor crews with Granite Construction will also repair and repave nearly 1 mile of State Route 9 at the junction with…
Project

US 2 - Eagle Falls Vic to Tye Creek - Bridge Decks Overlay - Complete Summer 2021

Timeline: Spring 2020 to Summer 2021
  • Road
  • Completed
  • Snohomish County
  • King County
In 2020 and 2021, contractor crews will repair the bridge decks on nearly two dozen structures along US 2 between the area west of Index (Proctor Creek/Big Bend) and Skykomish (Tye River vicinity).
Project

US 2 - Median Barrier - Complete April 2021

Timeline: Winter 2021 to March 2021
  • Road
  • Completed
  • Snohomish County
In 2021, WSDOT installed a concrete median barrier on US 2 between Bickford Avenue and the area just east of the SR 9 interchange in Snohomish.
Project

US 2 - Reardan to Davenport Paving - Complete August 2022

Timeline: May 2022 - June 2022
  • Road
  • Completed
  • Spokane County
The pavement conditions within the limits of this project on US 2 have fallen below an acceptable rating. This project will rehabilitate the roadway along this section to preserve the pavement and pavement structure.
Project

US 2 - US 97 Easy St Roundabout - Complete July 2023

Timeline: Present - Summer 2023
  • Road
  • Completed
  • Chelan County
This project will improve mobility and reduce collision severity at the intersection of US 2/97 and Easy Street in Wenatchee, by constructing a multi-lane roundabout at the existing signalized intersection. Other improvements including transit pull outs and extension of the Apple Capital Loop…
Project

US 2 Grotto Vicinity Slope Stabilization - Complete December 2023

Timeline: October 2023 - December 2023
  • Road
  • Completed
  • King County
In fall 2023, we built two debris flow fences on the north side of US 2 near milepost 44, or approximately four miles northwest of Skykomish. These fences will help mitigate risk to two culvert inlets, reducing the chances a potential debris flow from the Bolt Creek burn scar could clog them and…
Project

US 2 Trestle Capacity Improvements & Westbound Trestle Replacement

Timeline: August 2023 - August 2025
  • Road
  • Pre-construction
  • Snohomish County
The US 2 trestle in Snohomish County is the only direct highway route across the Snohomish River to Interstate 5 (I-5). The US 2 Trestle Capacity Improvements & Westbound Trestle Replacement project begins with a Planning and Environmental Linkages (PEL) study. Federal PEL studies allow us to…
Project

US 2 West of Leavenworth Slope Stabilization

Timeline: July 2025-October 2025
  • Road
  • Not started
  • Chelan County
The project will increase safety for the public on the US 2 corridor by addressing four slopes with a history of active rockfall. The project will reduce the risk of rockfall by repairing damaged slope stabilization systems at three rock slopes and by scaling loose rock at the remaining rock slope…
Project

US 2 – Colbert Rd Intersection Revision - Complete October 2023

Timeline: June 2023 - October 2023
  • Road
  • Completed
  • Spokane County
This project improves the safety at the US 2 and Colbert Road intersection in North Spokane County by installing J-Turns. WSDOT was able to secure funding to improve safety by adding J-Turns also known as RCUT's (Restricted Crossing U-Turn Intersection) to reduce the number of conflict points…
Project

US 2 – Creston to Rocklyn - Paving - Complete June 2023

Timeline: Spring 2023 - Summer 2023
  • Road
  • Completed
  • Lincoln County
This project will rehabilitate roughly 15 miles of US 2 from the town of Creston to approximately five miles west of Davenport at Rocklyn Road in Lincoln County. Once the project is completed by grinding and inlaying new HMA (Hot Mix Asphalt), the roadway surface will have a smoother ride that will…
Project

US 2 – Spokane County Line to SR 211 – Paving

Timeline: August 2024 - October 2024
  • Road
  • Construction
  • Pend Oreille County
This project will rehabilitate roughly 26 lane miles of US 2 from the Spokane County line to State Route 211 in Pend Oreille County. This project will grind and inlay new HMA (Hot Mix Asphalt), the roadway surface will have a smoother ride that will be preserved for years to come.
Project

US 2 – Sunset Interchange - Illumination Replacement - Complete November 2023

Timeline: July 2023 - September 2023
  • Road
  • Completed
  • Spokane County
This project will replace the luminaires on US 2 at the Sunset Highway interchange in Spokane County. The aging illumination system will be replaced with modern components including LED light fixtures which will save on maintenance and energy costs for years to come. Illumination systems will be…
Project

US 2/Corridor Safety Improvements

Timeline: Late 2025 – Late 2026
  • Road
  • Pre-construction
  • Snohomish County
This project will improve pedestrian and traffic safety on US 2 at 11 locations by replacing the signalized intersection in Sultan at US 2 and Old Owen Road/Fern Bluff Road with a roundabout and installing delineation, signing, truck aprons, curb ramps, curbing and crosswalks along the US 2…
Project

US 2/Sexton Creek to Pilchuck River Fish Passage

Timeline: Spring 2025 - Fall 2025
  • Road
  • Pre-construction
  • Snohomish County
This project will remove a fish passage barrier on US 2 at Sexton Creek just south of Three Lakes Road near Snohomish. Contractor crews working for WSDOT will remove the two existing 5-foot steel culverts that run for over 180 feet under US 2 and replace them with a fish-passable structure. This…
Project

US 395 - Colville to Columbia River - Paving - Complete September 2022

Timeline: July 2022 - September 2022
  • Road
  • Completed
  • Stevens County
This project will rehabilitate roughly 11 miles of US 395 from the north end of Colville to the east bank of the Columbia River in Stevens County. Once the project is completed by removing the surface of the existing pavement, repairing portions of the pavement through crack sealing, paving with…

166,800 electric vehicle

registrations in Washington in 2023, up from 114,600 in 2022.

87 wetland compensation sites

actively monitored on 918 acres in 2023.

25,000 safe animal crossings

in the Snoqualmie Pass East Project area since 2014.