• Project

East of Vantage to Moses Lake project

Project overview

This project will consist of planing and paving the right, eastbound driving lane on Interstate 90from milepost 138.26 to milepost 148.44, and the eastbound driving lanes on Interstate 90 from milepost 164.15 to milepost 175.84. Other items include permanent signing, pavement markings, shoulder repair, pavement repair, joint seal, bridge joint seal, crack seal and fog seal existing shoulder.

Timeline
July 2025-October 2025
Project status
Not started
Funding
$8 million

What to expect

This is one of two projects occurring almost immediately adjacent to each other. Visit the Interstate 90 Vantage Bridge Deck Replacement and Special Repairs project page for more information.

Travelers will encounter single-lane closures throughout the duration of the East of Vantage to Moses Lake project during working hours. In addition, there will be travel advisories prior to the project reminding motorists of the upcoming closures.

During the planning and paving part of the project, speed will be reduced from 55 mph to 40 mph as a recommendation. Travelers will also encounter short-term ramp closures during working hours, and traffic will be detoured to the nearest interchange to the closed ramps.

Working hours will be as follows:

For Section 1 (Vantage to George): Night work, from 7 p.m. to 6 a.m.

For Section 2 (Dodson Road to Mae Valley): Day work, from 6 a.m. to 6 p.m.

This map shows the length of the project's two sections on Interstate 90, from Vantage to George (Section 1), and from Dodson Road to just west of Moses Lake, near Mae Valley (Section 2).