Project overview
This project will remove five barriers to fish under SR 109 on the Quinault Indian Nation.
Timeline
Fall 2025 - Fall 2027
Project status
Not started
Funding
See funding tab for additional information
Project hotline
What to expect
Proposed timeline
- Fall 2025 – Potential for utility relocation.
- Spring 2026 – Start of temporary bypass roads construction and relocation of remaining utilities.
- Summer 2026 – Temporary detour road opens to one-way alternating traffic.
- Fall 2026 – Construction completed at milepost 37.4 and 33.8.
- Winter 2026/Spring 2027 – Potential for non-weather dependent work that is not inside each stream.
- Summer 2027 – Construction resumes.
- Fall 2027 – Construction completed at mileposts 36.4, 36.8, and 33.1.
See 'maps and drawings' for each location.