SR 109 Ocean City to Taholah – Remove Fish Barriers

Visit our online open house for additional information. 

Project overview

This project will remove five barriers to fish under SR 109 on the Quinault Indian Nation.

Timeline
Fall 2025 - Fall 2027
Project status
Not started
Funding
See funding tab for additional information
Project hotline

What to expect

Proposed timeline 

  • Fall 2025 – Potential for utility relocation.
  • Spring 2026 – Start of temporary bypass roads construction and relocation of remaining utilities.
  • Summer 2026 – Temporary detour road opens to one-way alternating traffic. 
  • Fall 2026 – Construction completed at milepost 37.4 and 33.8. 
  • Winter 2026/Spring 2027 – Potential for non-weather dependent work that is not inside each stream.
  • Summer 2027 – Construction resumes.
  • Fall 2027 – Construction completed at mileposts 36.4, 36.8, and 33.1.

See 'maps and drawings' for each location.