• Project

I-90 – Rosamond Bridge Deck Rehabilitation - Complete August 2023

Project overview

This project will rehabilitate the concrete deck of the I-90 overcrossing at Rosamond Avenue in Spokane. Crews will repair delaminated and deteriorated areas and apply a protective inlay to provide a sound, smooth surface, prevent further corrosion of the reinforcing steel, and preserve structural integrity of the bridge deck for years to come.

Timeline
June 2023 - November 2023
Project status
Completed
Funding
$1 Million
Project hotline

What to expect

This project was completed on August 23, 2023. There are no impacts to the traveling public. 

Project map location for the Rosamond Bridge Deck Rehabilitation project above I-90 in Spokane County.